ASDA pins scheme

Our rope access inspection technicians spent 4 months of nightshifts within ASDA stores nationwide, operating MEWP’s and aid climbing within the structural steelwork of the store ceilings to inspect the structural pins, and to carry out minor remedial repairs where necessary.

ASDA pins scheme

Our rope access inspection technicians spent 4 months of nightshifts within ASDA stores nationwide, operating MEWP’s and aid climbing within the structural steelwork of the store ceilings to inspect the structural pins, and to carry out minor remedial repairs where necessary.

Mode of access: Rope Access, MEWP

Task in hand: Structural inspection. Remedial repairs

Location: UK wide

Team Size: 6

Duration: 6 months

Following completion of Phase 1: Inspection, two further months of night shifts commenced as phase 2, to carry out more major repairs identified at inspection.